Details of the work done as on 27th November 2007.
Component |
Foundation |
Columns & Ties |
Roofing |
Flooring |
Mechanical |
Electrical |
Tipping floor |
Completed |
Completed columns. |
Completed fabrication.
Started errection |
Completed soling. |
N.A |
Yet to start |
Presorting shed |
Completed |
Completed columns. |
Completed fabrication. |
Completed soling. |
Started fabrication |
Yet to start |
Treatment platform |
Completed |
Completed columns.
Started ties. |
Completed fabrication.
Completed errection of 4 trusses |
60 % completed |
N.A |
Yet to start |
Compost process shed |
Completed |
Completed columns. |
Completed fabrication. |
Yet to start |
Started fabrication |
Yet to start |
Finished products go down |
Completed |
Completed columns. |
Started fabrication |
Yet to start |
Started fabrication |
Yet to start |
Vermi compost shed |
42 piles and pile caps are to be completed. |
26 columns are to be completed |
Completed fabrication. |
Yet to start |
N.A |
Yet to start |
Effluent treatment plant |
Completed |
Completed columns. |
Started fabrication |
N.A |
Started fabrication |
Yet to start |
Administrative building |
Completed |
Completed columns. |
Yet to start. |
Completed |
N.A |
Yet to start |
Other amenities |
Completed |
Completed columns. |
Completed roofing for security cabin |
Completed |
N.A |
Yet to start |
Roads, drains & fencing |
N A |
N.A |
N.A |
Yet to start |
N.A |
Yet to start |